The construction of the Noord/Zuidlijn will begin with the building of the underground part of the Noord/Zuidlijn between Central Station and the future Ceintuurbaan Station. This stretch also contains the most difficult sections of the Noord/Zuidlijn, both technically and in terms of its integration within the city

The Rokin, Vijzelgracht and Ceintuurbaan stations will be built first. The building activities inside and in front of Central Station likewise began in early 2003, as did the construction of the shield-launching shaft for the tunnel-boring machine. The completion of the metro line is scheduled for 2015.

The stations

Rokin Station:
Start of construction: January 2003
Finished: late 2008

Vijzelgracht Station:
Start of construction: April 2003
Finished: late 2008

Ceintuurbaan Station:
Start of construction: April 2003
Finished: late 2008

Central Station:
Start of construction: late 2002
Finished: 2009

Download
Here you can download the most recent version of the project planning.

 

 
 
  Information Centre Stationsplein 7  
  Publications  
  FAQs  
  Planning  
  Archaeology  
  Photo and video  
 
  Print this page
Search Zoek
menu-itemmenu-item
menu-itemHome
menu-itemStations
menu-itemEngineering & Safety
menu-itemFor the neighbourhood
menu-itemBackground
menu-itemWant to know more?
menu-itemmenu-item
Dutch site
Sitemap
Contact
Links
 9 september 2010
© Gemeente Amsterdam
[+] Disclaimer